Recently, the Zhejiang Provincial Development and Reform Commission issued a notice on the “Addition and Exit List of Provincial Key Construction Projects in 2018â€, and 43 projects will withdraw from the list of key provincial construction projects. Among them, Zhejiang Jinli Environmental Protection Paper Co., Ltd. is also covered by an annual output of 1 million tons of environmentally-friendly recycled high-grade packaging paper.
The investment is about 3.8 billion, which is the largest investment in the history of the local area.
Jinli Paper has an annual output of 1 million tons of environmentally-friendly recycled high-grade packaging paper project and supporting construction of solid waste incineration cogeneration project. The total planned investment is about 3.8 billion yuan. It is invested and constructed by Zhejiang Jinlong Paper Co., Ltd., Longyou County, Cangzhou City, Zhejiang Province. The largest investment ever in the history of the country.
According to the statistics of Zhejiang Provincial Bureau of Statistics, in 2016, Zhejiang Jinlong Paper Co., Ltd. produced about 484,000 tons of boxboard, corrugated paper and specialty paper, and its main business income reached 161.565 million yuan. Among the papermaking enterprises, it ranks ninth.
The project was originally planned to be constructed in two phases, with a total of four paper machines. The first phase included 300,000 tons of gray board paper and 200,000 tons of corrugated paper; the second phase included 200,000 tons of high-watt and 300,000 tons of cardboard.
Exit due to the start of the work, partly due to investment progress
Why is such a large investment, why will it be withdrawn from the list of key construction projects? It is understood that the main reason may be due to zero start or slow progress.
The person in charge of the relevant department of the Zhejiang Development and Reform Commission said in an interview: "The projects that can be withdrawn can be classified into several categories. One is a zombie project, which is a delay in starting work; the other is slow progress, opening and closing; there is another category. It is a business operation, such as changes in the market and affecting the progress of investment."
According to the person in charge, according to the requirements, the provincial key construction projects need to start construction in the same year. These projects were withdrawn. The main reason is that the preliminary work was not in place and the conditions for starting the work were not met. Therefore, most of the projects that were withdrawn were unstarted or slow to start. project.
It is reported that the implementation of this exit mechanism in Zhejiang Province is mainly to solve the problem that the key projects are too much and the key points are not outstanding. Through such withdrawal and addition, the key points of key construction projects are more prominent, especially the infrastructure construction and shortcomings. board.
However, withdrawing from the provincial key construction projects does not mean that the project cannot continue to be implemented. The person in charge of the relevant department of the Zhejiang Provincial Development and Reform Commission said: "Exiting the key construction projects of the province does not mean that this project will not be done. After the withdrawal, it will not be done, depending on the local government or the invested enterprise."
This article is posted on the website for the purpose of transmitting more information and does not imply endorsement of its views or confirmation of its description.
Article source address: http://
Copier Toner For Ricoh,Newly Compatible Printer Cartridge,Ricoh Mpc2503 Toner,Cheap Ricoh Toner Cartridge
jiangmen jinheng office equipment Co. Ltd. , https://www.jmjhtonercartridge.com